Interlock system keeps parts flying between stations

Casper, Phillips & Associates Inc (CPA) was contracted by a large commercial aeroplane manufacturer to design a system to be carry parts between bridge cranes and workstations. The bridge cranes pick up the parts from a workstation and take them to the next workstation on the assembly line. The automated manufacturing process was for a […]

09/11/2021 - 15:07 pm
Modulift HS2

Modulift delivers custom 25t lifting frames for High Speed 2 

Modulift have designed, manufactured and delivered two custom lifting frames for the High Speed 2 (HS2) project in just six weeks.   Their team of engineers were asked to provide a bespoke lifting solution that would lift high speed railcar panels in two separate locations. The first lifting frame is being used at Southampton Docks […]

03/12/2020 - 15:54 pm

New Issue

LHI March 2024

In this month's issue